Review | Major System/Platform Variant | Original Planned | Current Planned | Achieved/Forecast | Variance (Months) |
System Requirements | Mk3E Combat Management System/Phased Array Radar - Stage 1(Requirements Review) | Mar 06 | - | May 06 | 2 |
Mk3E Combat Management System - Stage 2 (Requirements Review) | N/A | - | Aug 09 | N/A | |
Mk3E Combat Management System/Phased Array Radar - Stage 1 (Functional Review) | Jun 06 | - | Aug 06 | 2 | |
Preliminary Design | Mk3E Combat Management System/Phased Array Radar Preliminary Design Review | Dec 06 | - | Aug 07 | 8 |
ASMD Shore Facilities (HMAS Stirling) | N/A | - | Aug 08 | N/A | |
Critical/Detailed (PAR) Design | Mk3E Combat Management System (Phased Array Radar integration) - Stage 1 Critical Design Review - Part 2 | Dec 07 | - | Aug 08 | 8 |
Mk3E Combat Management System -Stage 2 Critical Design Review | N/A | Nov 10 | Nov 10 | 0 | |
ASMD Shore Facilities (HMAS Stirling) | N/A | - | Dec 08 | N/A | |
Phased Array Radar | Oct 07 | - | Oct 07 | 0 | |
Variance Explanations | Variance in design reviews is directly related to the change of acquisition strategy (movement from an eight ship program to a single ship program) or delay in initial contract award for phased array radar system. | ||||