| Test and Evaluation | Major System/ Platform Variant | Original Planned | Current Planned | Achieved/ Forecast | Variance (Months) |
| Test Readiness Review | HMAS Perth with upgraded ASMD System (Mk3E Combat Management System/Phased Array Radar System/Navigation Radar System - Harbour Phase) | Dec 08 | Aug 10 | Aug 10 | 20 |
| Acceptance (Initial Operational Capability - IOC) | HMAS Perth with upgraded ASMD System (Mk3E Combat Management System/Navigation Radar System) | Dec 09 | Jun 11 | Jun 11 | 18 |
| Variance Explanations | Variance in both the test readiness review and acceptance of the first upgraded ASMD ship is directly related to the change of acquisition strategy and movement from an eight ship program to a single ship program. | ||||