Description | Remedial Action | |
Due to technical problems (which have since been rectified), the phased array radar system factory acceptance testing for the lead ship has been delayed by six months. | Noting the developmental nature of the phased array radar, a significant level of float was placed in the schedule for this important acceptance testing. This, together with the flexibility in the production (installation) phase of the Project into the lead ship has resulted in no impact to the overall lead ship production schedule. | |