5.1  Key Lessons Learned

Project Lesson Category of Systemic Lessons

Ensure that technically complex developmental projects, that have high levels of risk as part of the new system or integration of the new system into existing systems, demands that a prototype (lead platform) be agreed up front and used for proving the capability before agreeing to additional platforms.

First of Type Equipment

Adequate communication between, and engagement of, critical stakeholders to ensure that a common understanding of Project status is maintained.

Governance