2.1 Project Budget History

Date

Description

Base Date $m

Current $m

Contractor

Notes

Sep 02

Original Approved

455.3

455.3

May 03

Real Variation - Transfers

(0.9)

(0.9)

1

Aug 04

Real Variation -Budgetary Adjustments

(0.8)

(0.8)

2

(1.7)

(1.7)

30 Jun 10

Price Indexation

55.5

30 Jun 10

Exchange Variation

(51.1)

30 Jun 10

Total Budget

453.6

458.0