Item | Original Planned | Achieved/Forecast | Variance (Months) | Variance Explanations/ Implications |
Mar 08 | May 08 | 2 | The RCS baseline (CS04) installed in HMA WALLER and FARNCOMB was approved for IOR by Chief of Navy in May 2008 and September 2009 respectively. Chief of Navy subsequently approved Operational Release of that baseline on 9 December 2009. The capability delivered by the project is consistent with the MAA and IOC will be achieved when the Capability Manager confirms all other Fundamental Inputs to Capability (FIC) are complete. |