Identified Risk (risk identified by standard project risk management processes) | ||
Description Remedial Action | ||
There is a possibility that the replacement combat system installation schedule will be affected by on-going changes to the FCD schedule and boat availability, leading to schedule extensions and significant cost increases to be borne by the project. | This risk is being treated by: • Monitoring the impact of a revised Usage Upkeep cycle. • Establishing project prolongation costs. • Assigning contingency funding to the last boat installation. • Monitoring remaining project funds and budget spend. | |
There is a possibility that the Tactical Command Control System baseline will be affected by unforseen US Navy led baseline changes leading to an impact on cost and schedule. | • This risk has been retired. | |
Emergent Risks (risk not previously identified but has emerged during 2009-10) | ||
Description | Remedial Action | |
There is a possibility that completion of Category 3 and 4 Testing of future system integration and boat installations will be affected by a shortage of skilled personnel leading to an impact on schedule. | This risk is being treated by: • Engaging with project stakeholders to limit the loss impact of contractor expertise. • Seeking ways to mitigate the consequences of personnel turn-over and loss of expertise. • Initiating early recruitment action to replace personnel turn-over and to mitigate recruitment lead-times. • Initiating action to transfer knowledge and to share knowledge across the organisation. • Recruiting to maximum salary budget and Full-Time Equivalent manning numbers. | |