3.3  Progress toward Initial Operational Capability

Item

Original Planned

Achieved/Forecast

Variance (Months)

Variance Explanations/Implications

Initial Operational Release (Platform Modifications and Spiral 1)

Feb 08

May 08

3

Variance is attributable to the Navy Regulatory Review process.

Initial Operational Release (Spiral 4)

Nov 12

Nov 12

N/A

Dependent upon US Government acquisition process.