| Item | Original Planned | Achieved/Forecast | Variance (Months) | Variance Explanations/Implications |
| Operational Release Platform Modifications and Spiral 1) | Jan 10 | Mar 10 | 2 | Variance is attributable to the Navy Regulatory Review process. |
| Final Operational Capability (Spiral 4) | Nov 13 | Nov 13 |
| Achievement of FOC is dependent on Navy. The capability delivered by the project is consistent with the MAA and FOC will be achieved when the Capability Manager confirms all other Fundamental Inputs to Capability (FIC) are complete. |
Schedule Status as at 30 Jun 10
| Approval | ||
| Jul 01 | May 08 | Nov 13 |
|
| ||