3.4 Progress toward Final Operational Capability

Item

Original Planned

Achieved/Forecast

Variance (Months)

Variance Explanations/Implications

Operational Release Platform Modifications and Spiral 1)

Jan 10

Mar 10

2

Variance is attributable to the Navy Regulatory Review process.

Final Operational Capability (Spiral 4)

Nov 13

Nov 13

Achievement of FOC is dependent on Navy. The capability delivered by the project is consistent with the MAA and FOC will be achieved when the Capability Manager confirms all other Fundamental Inputs to Capability (FIC) are complete.

Schedule Status as at 30 Jun 10

Approval

IOC

FOC

Jul 01

May 08

Nov 13