2.2 Project Expenditure History
| Date | Description | Base Date $m | Current $m | Contractor | Notes |
| Prior to Jun 09 | | | 167.4 | | ASC Pty Ltd | 8 |
| | | | 107.6 | | Other | 7 |
| | | | | 275.0 | | |
| FY to Jun 10 | | | 22.1 | | ASC Pty Ltd | 8 |
| | | | 2.2 | | Other | 9 |
| | | | | 24.3 | | |
| Jun 10 | Total Expenditure | | | 299.3 | | |
| | | | | | | |
| Jun 10 | Remaining Budget | | | 108.4 | | |
| | | | | | | |