Part 3. Auditor-General's Review, CEO DMO Statement and Project Data Summary Sheets
>
FOLLOW-ON STAND OFF WEAPON
>
Section 1 - Project Summary
>
1.3 Project Approvals
1.3 Project Approvals
Approval
Original Planned
Achieved
Variance
First Pass
N/A
Dec 03
N/A
Second Pass
Dec 05
Dec 05
0