| Maturity Score | Attributes | ||||||||
| Schedule | Cost | Requirement | Technical Understanding | Technical Difficulty | Commercial | Operations and Support | Total | ||
| Project Stage: System Integration and Test | Benchmark 7 | 8 | 8 | 8 | 8 | 8 | 8 | 55 | |
| Current Project 7 | 7 | 8 | 7 | 8 | 8 | 7 | 52 | ||
| Explanation | • Cost: Final missile production costs are pending final USAF JASSM Lot 8 contract pricing negotiations. • Technical Understanding: Anomalies discovered during platform software integration have required extensive testing and redevelopment to ensure airworthiness and operational effectiveness. • Operations and Support: Operational and Support elements are being procured. System Acceptance cannot be finalized until completion of Operational Test and Evaluation. | ||||||||
| Project Stage | Total Benchmark Score | Total Current Score |
| System Integration and Test | 55 | 52 |
|
| ||