2.2 Project Expenditure History
Date | Description | Base Date $m | Current $m | Contractor | Notes |
Prior to Jun 09 | | | 71.3 | | Government ( Cases) | 2 |
| | | 60.5 | | Lockheed Martin | |
| | | 23.1 | | Other | 3 |
| | | | 154.9 | | |
FY to Jun 10 | | | 28.2 | | Government ( Cases) | 2 |
| | | 12.7 | | Lockheed Martin | |
| | | 4.7 | | Other | 4 |
| | | | 45.6 | | |
Jun 10 | Total Expenditure | | | 200.5 | | |
| | | | | | |
Jun 10 | Remaining Budget | | | 199.1 | | |
| | | | | | |