| Review | Major System/ Platform Variant | Original Planned | Current Planned | Achieved/Forecast | Variance (Months) |
| Prior Certification | AGM 158A-4 Missile System | Aug 06 | Jan 07 | Feb 07 | 6(1) |
| System Requirements | AGM 158A-4 Missile System | Jun 07 | N/A | Jun 07 | 0 |
|
| AF/A-18 System Segment | Sep 05 | N/A | Sep 05 |
|
| Preliminary Design | AGM-158A-4 Missile System | (2) | N/A | N/A | N/A |
|
| AF/A-18 System Segment | Mar 06 | N/A | May 06 | 2(3) |
| Critical Design | AGM 158A-4 Missile System | (2) | N/A | N/A | N/A |
|
| AF/A-18 System Segment | Aug 06 | N/A | Mar 07 | 7(3) |
| Build Readiness | AF/A-18 System Segment | Nov 07 | N/A | Jul 09 | 20(3) |
| Variance Explanations | (1) Variance due to protracted commercial contract negotiations. Prior Certification Review was completed in late Jan 07. The approval to exit the Prior Certification Review was dated 01 Feb 07. (2) The weapon is military-off-the-shelf (MOTS). Preliminary Design Review (PDR) and Critical Design Review (CDR) issues were addressed in the Prior Certification Review (PCR). (3) Data listed is for the F/A-18 21X Build 3 (JASSM functionality) Operational Flight Program software. Variance due to the detection of software anomalies and the undertaking of corrective and preventative action. | ||||