Item | Original Planned | Achieved/Forecast | Variance (Months) | Variance Explanations/Implications |
Dec 09 | Dec 11 | 24 | The AIR5418 Project Office is currently working toward achieving an Initial Materiel Release which will allow IOC by December 2011. The variance is attributable to delays in the AF/A-18 A/B software development and certification process, which has required extensive testing and redevelopment to ensure airworthiness and operational effectiveness. |