3.4  Progress toward Final Operational Capability

Item

Original Planned

Achieved/Forecast

Variance (Months)

Variance Explanations/Implications

FOC

Dec 10

Dec 12

24

FOC requires delivery of the approved full quantity of JASSM war stock. The FOC war stock missiles are being manufactured in Lot 8. The USAF contract for the Lot 8 missiles was delayed due to US JASSM program delays and missile reliability concerns.

Schedule Status as at 30 Jun 10

Approval

IOC

FOC

Dec 05

Dec 11

Dec 12