2.3 Contract Details

Contractor

Signature date

Price at signature (base) $m

Quantities at signature

Price at 30 Jun 10 (base)$m

Quantities at Jun 10

Equipment

Notes

SAAB Systems Pty Ltd

Apr 05

$123.1m

8

$119.7m

8

Combat Management Systems and Fire Control System upgrades

SAAB Systems Pty Ltd

Apr 07

$9.9m

N/A

$9.9m

N/A

First of Class (Lead Ship) Installation

BAE Systems Australia

Apr 05

$104.9m

8

$108.6m

8

Infrared Search and Track Systems

8

BAE Systems Australia

Apr 07

$26.2m

N/A

$26.2m

N/A

First of Class (Lead Ship) Installation

8

Major equipment received and quantities to 30 Jun 10

All major design reviews completed. Equipment has been delivered into store and is being appropriately maintained until required by Ph2B for its installation.

Notes

Note 1: 155.355 transferred to Project SEA1448 PH 2B for phased array radar procurement vice procurement of Very Short Range Air-Defence (VSRAD) capability as directed by Government.

Note 2: Transferred to DSG for facilities funding of the ASMD Systems Integration and Training Centre.

Note 3: Expenditure on the contract for upgrading the eight Combat Management Systems and Fire Control Systems.

Note 4: Expenditure on the contract for First of Class Installation of the Combat Management Systems and Fire Control System.

Note 5: Expenditure on the contract for eight Infrared Search and Track Systems.

Note 6: Expenditure on the contract for First of Class Installation of the Infrared Search and Track System.

Note 7: Other expenditure comprises: operating expenditure, contractors, consultants, contingency, other capital expenditure not attributable to the aforementioned top five contracts and minor contract expenditure.

Note 8: These contracts are listed with BAE Systems Australia who were formally Tenix Defence.