Test and Evaluation | Major System/Platform Variant | Original Planned | Current Planned | Achieved/Forecast | Variance (Months) |
Test Readiness Review | HMAS Perth with upgraded ASMD System (Mk3E Combat Management System/Fire Control Director/Infra-Red Search and Track - Sea Phase) | Nov 07 | Jan 11 | Jan 11 | 38 |
Acceptance | HMAS Perth with upgraded ASMD System (Mk3E Combat Management System/Fire Control Director/Infra-Red Search and Track - Sea Phase) | Apr 08 | Jun 11 | Jun 11 | 38 |
Variance Explanations | Variance indicated is directly linked to: the Government decision to investigate phased array radar technologies in lieu of the requirement for the VSRAD system; and, a realisation of technical risks in Phase 2B which required re-engineering effort to redesign the integration of the phased array radar into the ANZAC platform. | ||||