3.2  Contractor Test and Evaluation Progress

Test and Evaluation

Major System/Platform Variant

Original Planned

Current Planned

Achieved/Forecast

Variance (Months)

Test Readiness Review

HMAS Perth with upgraded ASMD System (Mk3E Combat Management System/Fire Control Director/Infra-Red Search and Track - Sea Phase)

Nov 07

Jan 11

Jan 11

38

Acceptance

HMAS Perth with upgraded ASMD System (Mk3E Combat Management System/Fire Control Director/Infra-Red Search and Track - Sea Phase)

Apr 08

Jun 11

Jun 11

38

Variance Explanations

Variance indicated is directly linked to: the Government decision to investigate phased array radar technologies in lieu of the requirement for the VSRAD system; and, a realisation of technical risks in Phase 2B which required re-engineering effort to redesign the integration of the phased array radar into the ANZAC platform.