Item | Original Planned | Achieved/Forecast | Variance (Months) | Variance Explanations/Implications |
Mar 08 | Jun 11 | 39 | Variance is directly linked to: the Government decision to investigate phased array radar technologies in lieu of the requirement for the VSRAD system; and, a realisation of technical risks in Phase 2B which required re-engineering effort to redesign the integration of the phased array radar into the ANZAC platform. |