3.4 Progress toward Final Operational Capability

Item

Original Planned

Achieved/Forecast

Variance (Months)

Variance Explanations/Implications

FOC

Dec 11

Apr 17

64

Variance is a result of the ASMD Project Management Stakeholder Group agreeing to link the completion date of this Phase of the Project with that of Phase 2B.

Schedule Status as at 30 Jun 10

Approval

IOC

FOC

Nov 03

Jun 11

Apr 17