4.1  Major Project Risks

Identified Risk (risk identified by standard project risk management processes)

Description

Remedial Action

There is a chance that any delays in phasedarray radar component of Phase 2B will impact installation of Phase 2A products.

The equipment being delivered under Phase 2A independently undergoes partial system test and system integration before being warehoused awaiting ship installation. As a result, equipment delivered under Phase 2A will be ready for installation pending outcomes from Phase 2B.

Recognising that the Infra-Red Search and Track System being installed under Phase 2A is a new capability being fielded by the RAN for the first time, there is a chance it will not operate to the expectations.

Project has had an operational system at the ANZAC Systems Support Centre in Western Australia since the end of 2007 and has been ensuring that the RAN have been actively involved in its testing and operation.

Emergent Risks (risk not previously identified but has emerged during 2009-10)

Description

Remedial Action

Nil

Nil