There are lessons to be learned from this case

8 Lessons include:

Wherever possible, LUL needs to recover costs from a third party which is partly, or fully, at fault for a problem (where the Infracos are not at fault), taking account of the impact on the price of the contract.

The need for better maintenance work and accompanying oversight, which all parties are attending to, e.g. covering and cleaning the pots; regular inspections by Infracos.

The need for better communications between the parties.