But there were weaknesses in planning and response

8  Weaknesses included:

  LUL relied on a single source for weather forecasts, the output of which conflicted with television and radio forecasts that predicted heavy snow much further in advance.

  Manual de-icing of the track by drivers with brushes could not keep pace with the speed of the downpour.

  Train sleet brushes and anti-icing systems were insufficient to deal with the rapid build up of snow under the train shoes.

  Infraco JNP did not meet all its responsibilities for ensuring the correct fluid was in the anti-icing units and sequencing of the anti-icing trains on the Northern Line in the correct formation, in order that all the track is de-iced consistently.