3. Land issues

Under the hub programme, the Procuring Authority ("Participant") retains ownership of the land and anything built by sub-hubco on it, i.e.:

• Sub-hubco does NOT lease the land to the Participant;

• The Participant grants sub-hubco a licence to occupy the land to the extent required to perform the services;

• The Participant will be required to warrant the title to the site; and

• The Participant may grant sub-leases of the facility to other bodies i.e. GP Practices