Risk is inherent in all PPP projects as in any other infrastructure projects. The main types of risks include:
| • Construction risk (mainly delays in construction) • Technology risk (arises when the technology is not a proven one) | Types of risk in a PPP |
|
| |
| • Sponsor risk (ability of the sponsor to deliver the project) • Environmental risk • Commercial risk (lower than expected demand for services produced by the project) • Operating risk (inefficiency in operation leading to higher operating cost) • Legal risk (change in law) • Regulatory risk (change in regulatory regimes) • Political risk (change in government policy) • Force majeure (risks due to unpredictable natural and man-made events such as earth quake, flood, civil war, etc.) |
| An important aspect of PPPs is an explicit arrangement for sharing of risks between parties involved. Many different techniques ranging from rule of thumb (based on past experiences) to sophisticated simulation models are available for the assessment of different risks in a project.38 A risk matrix is developed after assessing risks in quantitative and/or qualitative terms for all possible risk factors. PPP contracts often include incentives that reward private partners for mitigating risk factors. An example of a risk matrix has been in Appendix 2.39 Though it is set up from the perspective of the government, it provides an example of how risks can be identified, assessed, and mitigated. | Risk matrix |
|
|
| The risk matrix identifies the risks, their magnitudes and possible mitigation measures and serves as a useful tool for the purpose of sharing risks between the parties. The general principle is that project risks are allocated to the party that is the best equipped to manage them most cost effectively. For example, political and regulatory risks are more appropriate to the public sector while construction and operating risks are more suited to the private sector. The allocation of commercial risks is generally more common to the private sector. However, in certain cases, a part of the commercial risks due to lower than expected demand for services produced by the project may be shared by the public sector. In such cases normally a provision is also set to share any excess revenue if the demand exceeds the expected level. Table 3 provides an example of an arrangement for sharing of various risks. | What the risk matrix shows |
|
|
Table 3. A hypothetical risk allocation table
| Risk | Contractor | Operator | Equity | Lenders | Government | Insurance | Unallocated |
| 1. Construction overruns/delays | * |
| * |
|
|
|
|
| 2. Change in legal regimes |
| * |
|
| * | * |
|
| 3. Land acquisition |
|
|
|
| * |
|
|
| 4. Approvals/ licences/permits | * |
|
|
| * |
|
|
| 5. Variations | * | * |
|
| * |
|
|
| 6. Taxation | * |
| * | * | * |
|
|
| 7. Tariffs and charges |
| * | * |
| * |
|
|
| 8. Revenue/Traffic/ Demand |
|
| * | * | * |
|
|
| 9. Operation |
| * |
|
|
|
|
|
| 10. Maintenance |
| * |
|
|
|
|
|
| 11. Defects liability | * | * |
|
|
|
|
|
| 12. Natural disaster |
| * |
|
|
| * |
|
| 13. Industrial action |
| * | * |
| * |
|
|
| 14. Environmental |
|
| * |
| * |
|
|
| 15. Civil disobedience |
| * |
|
| * | * |
|
| 16. Insurance |
|
|
|
|
| * |
|
| 17. Force majeure |
| * | * |
| * | * | * |
| 18. Confiscation |
| * |
| * | * | * |
|
| 19. Interest rate risk |
|
| * | * |
|
|
|
| 20. Repatriation of capital and profit |
| * | * | * |
| * |
|
| Note: | Risks of political nature and some other types of risks (items 2 and 20, for example) can be covered by special risk guarantee instruments. See discussion below. |
| Source: | Adapted and modified from Antonio Estache and John Strong, The Rise, the Fall, and the Emergency Recovery of Project Finance in Transport, World Bank Institute. Available at <http://wbln0018.worldbank.org/Research/workpapers.nsf/0046a83407e91901852567e50051cc43/8b0290555c2424f3852569130063d5 ee?OpenDocument> |
| It is important to note that risk transfer is a key element in effective PPP design. If a good balance in sharing risk is not achieved, it will result in increased costs and the inability of one or both parties to fully realize their potential. The magnitude of project risks are also assessed as a part of the due diligence process undertaken by lenders. The higher the assessed/perceived risks of a project, lenders would charge a higher risk premium for lending money. Consequently, the financing cost of project becomes higher. This means, holding project capital and operating cost constant, the same project in a country with higher risk perceptions would require a higher tariff than in countries with lower risk perceptions. | The necessity of good balance in risk sharing risk sharing |
|
|
Generally mitigation measures are available for most risks. An effective strategy in risk management is to consider suitable mitigation measures for risks at the project planning stage. As appropriate, their consideration needs to be reflected in contract design and negotiation, and later on in designing a contract management process to address them during the construction and operation periods. The basic approaches to risk mitigation include:
• Transparency in the whole process including participation of key stakeholders from the beginning;
• Properly executed project appraisal with details of risks and their likely effects, and return expectations;
• Cash flow projections based on technical, market and financial analysis;
• Structured finance40 to meet the characteristics of the project;
• Security package and elaborate documentation;
• Project monitoring and contract compliance.
The following are some of the commonly applied tools for risk mitigation:
• Measures that can de-risk to the extent possible or minimize the possibility of risk occurrence
• Obligations and comforts in contract agreement through allocation of risks to identified parties with penalties and/or responsibilities for consequences Insurance when available
• Financial instruments (hedge, swap, etc.)
• Designing of financial structure to minimize the risk of default.
| The government can provide loan guarantees (partial or full) for a project to help reducing its risk level and thereby financing costs. This is also helpful to make a project commercially viable. If such a guarantee is available, investments risks can be assessed at the zero or no risk level (compared with sovereign borrowings). However, such guarantees expose the government to potential liabilities in the event of a loan default and as such have implications for fiscal discipline (see Chapter III). Further, full guarantee by government reduces the incentives for the private operator to manage the project risks. | Implications of loan guarantees |
|
|
| Multi-lateral agencies such as the Multilateral Investment Guarantee Agency or MIGA of the World Bank Group provide loan guarantee of developing country private sector projects. MIGA provides guarantee against foreign currency transfer restrictions, expropriation, breach of contract, war and civil disturbance. Many other development banks such as the Asian Development Bank, and ECAs have also similar mechanisms for providing loan guarantee to private projects. | Risk guarantee instruments |
|
|
Some countries have their own mechanism for providing loan guarantee.
In the Philippines, for example, there is a national agency that provides loan guarantee for projects undertaken by local government units (LGUs).
___________________________________________________________________________
38 General purpose and special purpose softwares are available for risk assessment of infrastructure projects. Inforisk is a special purpose software developed by the World Bank. There are also many general purpose softwares commercially available.
39 Reproduced with permission from the State of Victoria in Australia appropriate to the public sector while construction and operating risks are more suited to the private sector. The allocation of commercial risks is generally more common to the private sector. However, in certain cases, a part of the commercial risks due to lower than expected demand for services produced by the project may be shared by the public sector. In such cases normally a provision is also set to share any excess revenue if the demand exceeds the expected level. Table 3 provides an example of an arrangement for sharing of various risks.
40 In project finance (see Section C in this chapter), structured finance broadly means debt structured to fit the cash flow.