Procurement Options

a)  The hub programme has been developed to deliver improved value for money for projects of this nature and has an overarching business case setting out how this is achieved - no further evidence is required for selection of hub as procurement route;

b)  If a Local Authority seeks to use a different procurement route for a revenue funded school, it must discuss this with SFT and prepare a quantitative analysis demonstrating the life-cycle value for money improvements to be delivered.