| PS Ref | Performance Standard | Performance Monitoring | |||||
| Category | Response Period | Rectification Period | Monitoring Method | Performance Monitoring Period | Remedial Period / Remedy | ||
| Liaison | |||||||
| FM22 | Sub-hubco shall meet with the Authority's Representative at least monthly. | [Medium] | N/A | N/A | Scheduled meeting attended by designated Staff. | Monthly | 3 Business Days. |
| FM23 | Sub-hubco shall liaise with the relevant Authority's Representative, where works may impact on the Prescribed Operational Function. | [Major] | N/A | N/A | Relevant information submitted to Authority's Representative prior to commencement of works | Per occurrence | 2 Business Days. |
| FM24 | Sub-hubco shall provide information relating to Freedom of Information requests to the Authority's Representative in a timely manner in the agreed format and quality in accordance with Clause 61. | [Minor] | N/A | N/A | Information provided in the agreed format and quality by the agreed date. | Per request | 1 Business Day. |
| FM25 | Sub-hubco shall provide advice on consumption of Utilities at the Facilities and revenue cost implications throughout the Operational Term 6 months prior to capital / lifecycle estate upgrading/modernisation schemes and new developments as dictated by the 5-Year Maintenance Plan delivered to the Authority in accordance with Clause 23.11. | [Minor] | N/A | N/A | Information submitted in the agreed format and quality by the agreed date. | Per request | 1 Business Day. |
| FM26 | Sub-hubco shall participate in and support any joint utility working group formed by the Authority. | [Medium] | N/A | N/A | [Quarterly/bi-annual] meetings are attended. | Per request | 1 Business Days. |