| PS Ref | Performance Standard | Performance Monitoring | |||||
| Category | Response Period | Rectification Period | Monitoring Method | Performance Monitoring Period | Remedial Period / Remedy | ||
| Operating Efficiently | |||||||
| FM46 | Sub-hubco shall maintain the Facilities and perform its operations so as to minimise Utilities consumption whilst achieving the optimum environmental conditions required by the Authority. | [Medium] | N/A | N/A | Inspection of PPM inspection sheets and Utilities records. | Monthly | 3 Business Days. |
| FM47 | Sub-hubco shall manage and operate an effective Building Management System (as defined in Part 6 of the Schedule, (Board Construction Requirements). | [Major] | N/A | N/A | Inspection of records. | Daily | 2 Hours. |
| FM48 | Sub-hubco shall act in accordance with and support the Authority's energy strategy and environmental policies in the delivery of this service. | [Minor] | N/A | N/A | Review of Sub-hubco policies and procedures | Monthly | 5 Business Days. |