5.71 Detailed planning applications are not normally progressed until appointment of preferred bidder. A refusal to grant planning permission or the imposition of conditions may require changes to design, cost and project timetable. Provided such changes do not impact upon the basic features of the Final Tender they are not discriminatory and should not distort competition. They should therefore be acceptable under the competitive dialogue process.