Appendix 1: Indicative project timetable

Figure A.1 gives an example of the milestones and timetable for a major scheme from OJEU onwards which is following the competitive dialogue. The timetables should be regarded as indicative, and will need to be tailored to meet the needs of individual schemes. Note that Alcatel standstill requirements must be factored into the Preferred Bidder selection process. Relevant Key Stage Reviews must also be factored in.

Figure A.1: Indicative project timetable for major schemes

Stage

Duration

Cumulative Duration

 

 

 

Deadline for expression of interest & submission of PQQ submission

4 weeks

4 weeks

Evaluation of PQQ submissions and determine shortlist

4 weeks

8 weeks

Issue Invitation to Participate in Dialogue - Submission of First Tender

7 weeks

15 weeks

Evaluate Stage 1 submissions & Issue Stage 2 Instructions

4 weeks

19 weeks

Prepare & submit Stage 2 Submissions

7 weeks

26 weeks

Evaluate Stage 2 submissions & Issue Stage 3 Instructions

4 weeks

30 weeks

Prepare & submit Stage 3 Submissions

7 weeks

37 weeks

Evaluate Stage 3 submissions & Issue Stage 4 Instructions

4 weeks

41 weeks

Prepare & submit Stage 4 Submissions

7 weeks

48 weeks

Evaluate Stage 4 submissions & Issue Invitation to Submit Final Tender

4 weeks

52 weeks

Preparation and Submission of Final Tenders

7 weeks

59 weeks

Evaluate Final Tenders Prepare Key Stage review Announce Preferred Bidder

8 weeks

67 weeks

Finalise Contract Prepare FBC

10 weeks

77 weeks

FBC Approval and Award of Contract

1 week

78 weeks

Overall Procurement Period: Approximately 18 months  

This indicative timetable will be used to assess the NHSScotland bodies' proposed timetable during the Key Stage Review process. The actual timetable will be performance benchmarked thereafter.