9.9 The affordability calculations of any project must include an explicit allowance for the provision of IM&T and equipment regardless of whether they are to be procured using public funds or through PPP. The effect on affordability must be considered in the Outline Business Case as well as in the Full Business Case.
9.10 The decision on which, or what combination, of the three routes above should be followed is ultimately based on which offers best value for money taking into account the risks and degree of complexity associated with each method of procurement.