9. Residual Value Risks

No.

Risk Heading

Definition

Allocation

public sector

private sector

shared

9.1

Procuring entity no longer requires assets at end of contract

The risk that the procuring entity will wish to vacate the asset at the end of the contract period, and that the operator may be faced with decommissioning costs.