| No. | Risk Heading | Definition | Allocation | ||
|
|
|
| public sector | private sector | shared |
| 10.1 | Incorrect cost estimates for planning approval | Estimated cost of receiving detailed planning permission is incorrect, including the cost of satisfying unforeseen planning requirements. |
|
|
|
| 10.2 | Delayed planning approval | A delay in receiving planning permission may have broader cost implications for the project, as well as the loss of potential savings. |
|
|
|
| 10.3 | Land sale receipts | The estimated receipts from the sale of surplus land may be |
|
|
|
It should be noted that the above would require to be adjusted for project specific variations (e.g. soft FM position, inclusion of equipment etc.)