12.9 Contract amendments

12.9.1 Even though the Contracts Directive allows for amendments, contracts should not be amended unless such amendments are in the best interest of the government, because they save dollars or time, or because they facilitate the attainment of the primary objective of the contract. Work definitions should be carefully developed. Contracts should then be properly administered to avoid unanticipated amendments except to change the scope of the work. Amendments to existing contracts often call for more administrative work and little can be done through competition to encourage the contractor to do additional work or respond to changes at the lowest possible cost.

12.9.2 Every effort should be made to avoid:

1.  inadequate initial funding, resulting in amendments to increase the contract value;

2.  inadequate pre-planning, resulting in amendments to change the design, specifications or quantity involved; and

3.  improper administrative procedures, necessitating amendments to change the specifications and delivery or other requirement in order to protect the contractor or government agency involved.

12.9.3 Many contract amendments are, in fact, prudent. Often contract amendments or probable amendments can be foreseen when the initial contract is contemplated. In such cases, the proposal section of the approval document should indicate the likelihood of such amendments, including a maximum cost limit. Where Treasury Board or managerial approval is required and the original contract proposal to the Treasury Board or departmental management has been approved, subsequent amendments do not require the same level of approval as long as they are within the original intent of the proposal and applicable amendment authorities.

12.9.4 Extra costs. Departments and agencies are advised to include clauses for cost overruns in contracts. In situations where, the Crown has received no additional or apparent benefit and there is uncertainty whether a legal liability exists under the terms of the contract. Legal advice should be obtained as to whether the extra costs may be considered as an amendment to the contract. Additional payments should, in any event, cover only the additional reasonable costs incurred by the contractor and should be considered only if the circumstances were beyond the contractor's control and the contractor was without fault or negligence and could not reasonably have foreseen the actual circumstances at the time the contract was entered into. Each case will be treated on its own merits with payments allowed within delegated authorities and appropriate approvals sought in the event that the changes exceed authorities.