4 Operational Period

4.1 This section of the guidance covers the period from services commencement (i.e. when the unitary charge commences) to contract end. It highlights the key aspects of the management of the payment mechanism which need to be considered by a Procuring Authority in order to ensure the project operates as smoothly as possible. The specific areas covered in this section are:

o Operation of the Payment Mechanism - Grace Periods 

o Deduction Enforcement 

o Snagging Items

o Contract Changes

More Information