IN CONSIDERATION of the Board entering into the Project Agreement with Project Co and the due observance by Project Co of the obligations contained herein and in the Project Agreement, the Licensor shall permit and licence Project Co (which expression shall for the purposes of exercise of the rights granted pursuant to this Clause 2 include the Project Co Parties and any other party to whom Project Co's interest in the Board Project Documents (as defined in the Funders Direct Agreement) is transferred or novated from time to time in accordance with the terms of this Licence):-
2.1 From the date of issue of the Certificate of Commencement until the Actual Completion Date to:
2.1.1 exercise the Ancillary Rights; and
2.1.2 enter upon the Site
in each case for the purposes of implementing the Works and carrying out Project Co Pre-Completion Commissioning.
2.2 After the occurrence of the Actual Completion Date until the Expiry Date (or if earlier the Termination Date) to:
2.2.1 enter upon the Site solely for the purposes of:
2.2.1.1 the carrying out of Project Operations (other than those Project Operations which Project Co is licensed to carry out pursuant to Clause 2.1 above); and
2.2.1.2 remedying defects and the carrying out of Snagging Matters; and
2.2.2 exercise the Ancillary Rights.
2.3 The Scottish Ministers undertake that from the Commencement Date until the Expiry Date (or if earlier the Termination Date), the Scottish Ministers as heritable proprietors of the Site and the areas over which the Ancillary Rights are to be exercised shall not take any action on or affecting the Site or the exercise of the Ancillary Rights granted hereunder which would interfere with the Project Operations or prevent or restrict the use of the Site for the Authorised Purpose.