4.6  Termination After Novation

After the Novation Effective Date the Service Provider shall only be entitled to exercise its rights of termination under the Service Contract

4.6.1  in respect of any Event of Project Co Default arising after that date in accordance with the Service Contract; or

4.6.2  if the Proposed Substitute does not discharge the obligations and liabilities assumed by it under Clause 4.5.2(b) which relate to matters arising prior to the end of the Step-in Period within [fifteen (15)] Business Days following the Novation Effective Date.