6.1 The high level factors outlined above can be assessed and scored against a range of criteria and evaluation parameters. These are shown in the matrix provided in Figure 4 below.
6.2 The detailed qualitative assessment of the scheme is undertaken against factors in five weighted categories as set out in Figure 2 below:
Figure 2 - Qualitative Assessment - Weighting
Category | Weighting |
Capital Efficiency | 40% |
Revenue (Facilities Management) Efficiency | 20% |
Potential to Transfer Risk | 30% |
Residual Value | 5% |
Potential for alternative source of income | 5% |
6.3 Each parameter in Figure 4 should be considered and the extent to which the project provides scope to satisfy the requirements of the criteria should be scored using the following scale:
Figure 3 - Qualitative Scoring Scale
Extent of Contribution | Score |
No scope for the project to contribute | 0 |
Some scope for the project to contribute | 1 |
Good potential for the project to contribute | 2 |
The project offers scope to contribute significantly | 3 |
6.4 The score for each part of the matrix (A to E) in Figure 4 below should be totalled manually and the relevant score included in the shaded box at the end of each section. The totals should then be entered into Figure 5 and subsequently be multiplied by the weights as given in Figure 2 above to arrive at a weighted score. Finally, the weighted scores should be totalled to reach a final score.
Figure 4 - Detailed Qualitative Assessment for "PPP ability" of Potential Capital Scheme - Evaluation Parameters
| Scoring System 0 = No scope for the project to contribute 1 = Some scope for the project to contribute 2 = Good potential for the project to contribute 3 = The project offers scope to contribute significantly |
|
Major Criteria | PPP Opportunity | Detailed Test | Score (0-3) | Comments | ||
A | Potential for PPP to be more capital cost effective | A1 | Increase the scheme to generate economies of scale | • Enlarging the scheme to allow greater use by other users • Changing the quality and range of service provision of the scheme to make it more attractive to users • Adding extra facilities/services which cater for other customers |
|
|
Weighting = 40% | ||||||
| A2 | Design Innovation | • Adding in 'higher technology' or including built in technology upgrades to save labour or reduce other ongoing costs • Using new materials to provide a quicker build or cheaper capital expenditure • Using new building techniques through design team integration to provide lower maintenance and lifecycle costs • Redesigning the scheme in some way to make it more efficient and therefore possess a lower unitary charge |
|
| |
| A3 | Reduce NHS Capital Costs | • Changing the specified materials without altering the quality of the facility (and therefore no change to service standards), such as using either lower cost replaceable fittings or achieving a higher procurement discount • Tighter control over subcontractors who may take an equity stake in the project • Longer term materials that have lower replacement cycles such as high tech roofing • Redesigning the scheme in some other way to make it cheaper to build • Providing a higher level of integration of departmental services and therefore a smaller gross floor area (e.g. shared reception areas) |
|
| |
A OVERALL POTENTIAL FOR PPP TO BE MORE COST EFFECTIVE |
| (max. possible = 36) | ||||
Major Criteria | PPP Opportunity | Detailed Test | Score (0-3) | Comments | ||
B | Potential revenue efficiencies | B1 | Lower costs through economies of scale | • Provision by large multidisciplinary specialist FM providers |
|
|
Weighting = 20% | ||||||
| B2 | Lower costs through more efficient service provision | • Provision by specialist FM providers • Optimising the interface between build solutions and FM provision through design innovation • Working FM facility equipment for longer hours such as HSDU sterilisers, therefore reducing requirement for plant and/or machinery |
|
| |
| B3 | Sharing the facility with other users | • Enlarging the scheme for shared NHS and private sector use and sharing running costs and overheads |
|
| |
| B4 | Help increase effectiveness | • Increasing the throughput to take advantage of positive associations between higher volumes of work and better outcomes for patients • Changing the quality of the facility, or the embodied technology, to make it better for users • Redesigning the scheme in some other way, the better to suit users' requirements |
|
| |
B OVERALL POTENTIAL FOR PPP TO GENERATE FM SAVINGS |
| (max. possible = 24) | ||||
Major Criteria | PPP Opportunity | Detailed Test | Score (0-3) | Comments | ||
C | Potential risk transfer to private sector | C1 | Design risks | • Failure to design to brief and build to design. |
|
|
Weighting = 30% | ||||||
| C2 | Construction risks | • Incorrect time estimate, unforeseen ground conditions, on-site security, site safety, third party claims, delay events, force majeure, non NHS legislation, changes in taxation, contractor default, poor project management, contractor/sub contractor industrial action, building commissioning, availability of adequate labour, availability of construction materials |
|
| |
| C3 | Performance risks | • Latent defects, sub-contractors performance and default, industrial action, availability of facilities |
|
| |
| C4 | Operating cost risks | • Incorrect cost estimates, non NHS legislative change, inflation |
|
| |
| C5 | Revenue variability | • Third party income streams and demand |
|
| |
| C6 | Technology and obsolescence | • Buildings, plant and equipment may become obsolete during the contract |
|
| |
C OVERALL POTENTIAL TO TRANSFER RISK |
| (max. possible = 18) | ||||
Major Criteria | PPP Opportunity | Detailed Test | Score (0-3) | Comments | ||
D | Potential residual value and transfer of surplus land to private sector | D1 | Location of Land | • Location of facilities in relation to other healthcare facilities |
|
|
Weighting = 5% | ||||||
| D2 | Re-siting of the facility | • Constructing the new build facility closer to the edge of the site to achieve separate identity • Constructing facilities that could serve an alternative purpose such as hotel, conference or office accommodation if sited so as to be able to segregate from the health site at a later date |
|
| |
D OVERALL POTENTIAL FOR THE AVAILABILITY OF RESIDUAL VALUE |
| (max. possible = 9) | ||||
Major Criteria | PPP Opportunity | Detailed Test | Score (0-3) | Comments | ||
E | Potential for alternative source of income? | E1 | Recover its cost via user charges to make the scheme more financially free standing | • Making the facility/equipment/system larger or smaller and more profitable • Changing the quality of the facility/equipment and making it more profitable • Redesigning the scheme/project in some way so as to allow additional profitable uses |
|
|
Weighting =5% | ||||||
E OVERALL POTENTIAL FOR PRIVATE SECTOR TO GENERATE OTHER INCOME |
| (max. possible = 9) | ||||
6.5 The results of the above assessment should now be summarised in Figure 5 below:-
Figure 5 - Summary of Qualitative Assessment of "PPP ability"
Ref | Scheme Title | Capital Costs if Publicly Financed |
|
|
|
Summary of Assessment of Scope for PPP |
|
|
|
| Raw Score | Weighting | Weighted Score |
A Capital Efficiency B Revenue (FM) Efficiency C Risk Transfer D Residual Value E Alternative Income Stream | /36 /24 /18 /9 /9 | 40% 20% 30% 5% 5% |
|
WEIGHTED 'PPP ABILITY' SCORE |
|
|
|
Rating of Score |
| Indicated Action |
Score 0 - 25% = Minimal prospects for PPP/PFI |
| Unsuitable for PPP/PFI - public capital required |
Score 25-50% = Some prospects for PPP/PFI |
| Combine with other schemes, re-evaluate |
Score 50-75% = Good prospects for PPP/PFI |
| Review, re-evaluate and modify scheme to increase opportunities for securing best value |
Score 75%+ = Excellent prospects for PPP/PFI |
| Test scheme for PPP/PFI |
Note - the weighted score is calculated by multiplying the raw score per category by the weighting (e.g. if the score for Capital Efficiency were 27/36, then the weighted score would be 30.