6 External Factors - Qualitative Assessment

6.1  The high level factors outlined above can be assessed and scored against a range of criteria and evaluation parameters. These are shown in the matrix provided in Figure 4 below.

6.2  The detailed qualitative assessment of the scheme is undertaken against factors in five weighted categories as set out in Figure 2 below:

Figure 2 - Qualitative Assessment - Weighting

Category

Weighting

Capital Efficiency

40%

Revenue (Facilities Management) Efficiency

20%

Potential to Transfer Risk

30%

Residual Value

5%

Potential for alternative source of income

5%

6.3 Each parameter in Figure 4 should be considered and the extent to which the project provides scope to satisfy the requirements of the criteria should be scored using the following scale:

Figure 3 - Qualitative Scoring Scale

Extent of Contribution

Score

No scope for the project to contribute

0

Some scope for the project to contribute

1

Good potential for the project to contribute

2

The project offers scope to contribute significantly

3

6.4 The score for each part of the matrix (A to E) in Figure 4 below should be totalled manually and the relevant score included in the shaded  box at the end of each section. The totals should then be entered into Figure 5 and subsequently be multiplied by the weights as given in  Figure 2 above to arrive at a weighted score. Finally, the weighted scores should be totalled to reach a final score.

Figure 4 - Detailed Qualitative Assessment for "PPP ability" of Potential Capital Scheme - Evaluation Parameters

Ref

Scheme Title

 

 

 

Scoring System

0  = No scope for the project to contribute

1  = Some scope for the project to contribute

2  = Good potential for the project to contribute

3  = The project offers scope to contribute significantly

Capital Cost

 

 

 

Major Criteria

PPP Opportunity

Detailed Test

Score (0-3)

Comments

Potential for PPP to be more capital cost effective

A1

Increase the scheme to generate economies of scale

•  Enlarging the scheme to allow greater use by other users

•  Changing the quality and range of service provision of the scheme to make it more attractive to users

•  Adding extra facilities/services which cater for other customers

 

 

Weighting = 40%

 

A2

Design Innovation

•  Adding in 'higher technology' or including built in technology upgrades to save labour or reduce other ongoing costs

•  Using new materials to provide a quicker build or cheaper capital expenditure

•  Using new building techniques through design team integration to provide lower maintenance and lifecycle costs

•  Redesigning the scheme in some way to make it more efficient and therefore possess a lower unitary charge

 

 

 

A3

Reduce NHS Capital Costs

•  Changing the specified  materials without  altering the quality of the facility (and therefore no change to service standards), such as using either lower cost replaceable fittings or achieving a higher procurement discount

•  Tighter control over subcontractors who may take an equity stake in the project

•  Longer term materials that have lower replacement cycles such as high tech roofing

•  Redesigning the scheme in some other way to make it cheaper to build

•  Providing a higher level of integration of departmental services and therefore a smaller  gross  floor  area  (e.g.  shared reception areas)

 

 

A  OVERALL POTENTIAL FOR PPP TO BE MORE COST EFFECTIVE

 

(max. possible = 36)

Major Criteria

PPP Opportunity

Detailed Test

Score (0-3)

Comments

B

Potential revenue efficiencies

B1

Lower costs through economies of scale

•  Provision by large multidisciplinary specialist FM providers

 

 

Weighting = 20%

 

B2

Lower costs through more efficient service provision

•  Provision by specialist FM providers

•  Optimising the interface between build solutions and FM provision through design innovation

•  Working FM facility equipment for longer hours such as HSDU sterilisers, therefore reducing requirement for plant and/or machinery

 

 

 

B3

Sharing the facility with other users

•  Enlarging the scheme for shared NHS and  private sector use and sharing running costs and overheads

 

 

 

B4

Help increase effectiveness

•  Increasing the throughput to take advantage of positive associations between higher volumes of work and better outcomes for patients

•  Changing the quality of the facility, or the embodied technology, to make it better for users

•  Redesigning the scheme in some other way, the better to suit users' requirements

 

 

B  OVERALL POTENTIAL FOR PPP TO GENERATE FM SAVINGS

 

(max. possible = 24)

Major Criteria

PPP Opportunity

Detailed Test

Score (0-3)

Comments

C

Potential risk transfer to private sector

C1

Design risks

•  Failure to design to brief and build to design.

 

 

Weighting = 30%

 

C2

Construction risks

•  Incorrect time estimate, unforeseen ground conditions, on-site security, site safety, third party claims, delay events, force  majeure, non NHS  legislation, changes in taxation, contractor default, poor  project  management, contractor/sub  contractor  industrial action, building commissioning, availability of adequate labour, availability of construction materials

 

 

 

C3

Performance risks

•  Latent defects, sub-contractors performance  and  default,  industrial action, availability of facilities

 

 

 

C4

Operating cost risks

•  Incorrect cost estimates, non NHS legislative change, inflation

 

 

 

C5

Revenue variability

•  Third party income streams and demand

 

 

 

C6

Technology and obsolescence

•  Buildings, plant and equipment may become obsolete during the contract

 

 

C  OVERALL POTENTIAL TO TRANSFER RISK

 

(max. possible = 18)

Major Criteria

PPP Opportunity

Detailed Test

Score (0-3)

Comments

D

Potential residual value and transfer of surplus land to private sector

D1

Location of Land

•  Location of facilities in relation to other healthcare facilities

 

 

Weighting = 5%

 

D2

Re-siting of the facility

•  Constructing the new build facility closer to the edge of the site to achieve separate identity

•  Constructing facilities that could serve an alternative purpose such as hotel, conference  or office accommodation if sited so as to be able to segregate from the health site at a later date

 

 

D  OVERALL POTENTIAL FOR THE AVAILABILITY OF RESIDUAL VALUE

 

(max. possible = 9)

Major Criteria

PPP Opportunity

Detailed Test

Score (0-3)

Comments

E

Potential for alternative source of income?

E1

Recover its cost via user charges to make the scheme more financially free standing

•  Making the facility/equipment/system larger or smaller and more profitable

•  Changing the quality of the facility/equipment and making it more profitable

•  Redesigning the scheme/project in some way so as to allow additional profitable uses

 

 

Weighting =5%

E  OVERALL POTENTIAL FOR PRIVATE SECTOR TO GENERATE OTHER INCOME

 

(max. possible = 9)

6.5  The results of the above assessment should now be summarised in Figure 5 below:-

Figure 5 - Summary of Qualitative Assessment of "PPP ability"

Ref

Scheme Title

Capital Costs if Publicly Financed

 

 

 

 

Summary of Assessment of Scope for PPP

 

 

 

 

Raw Score

Weighting

Weighted Score

A  Capital Efficiency

B  Revenue (FM) Efficiency

C  Risk Transfer

D  Residual Value

E  Alternative Income Stream

/36

/24

/18

/9

/9

40%

20%

30%

5%

5%

 

WEIGHTED 'PPP ABILITY' SCORE

 

 

 

 

Rating of Score

 

Indicated Action

Score 0 - 25% = Minimal prospects for PPP/PFI

Unsuitable for PPP/PFI - public capital required

Score 25-50% = Some prospects for PPP/PFI

Combine with other schemes, re-evaluate

Score 50-75% = Good prospects for PPP/PFI

Review, re-evaluate and modify scheme to increase opportunities for securing best value

Score 75%+  = Excellent prospects for PPP/PFI

Test scheme for PPP/PFI

Note - the weighted score is calculated by multiplying the raw score per category by the weighting (e.g. if the score for Capital Efficiency were 27/36, then the weighted score would be 30.