The Base Payment is calculated in accordance with the following formula:
B = ∑ (BTn * BPn)
where:
BTn | The higher of a) the tonnage of Contract Waste Accepted; and b) the Minimum Tonnage of Contract Waste falling within Base Price Band 'n' in the relevant Contract Year except where the Contractor has failed to comply with Clause [refer to Clause dealing with substitution of Contract Waste] the Minimum Tonnage referred to shall be reduced by the tonnage of waste the Contractor would have secured if it had complied with its obligations under Clause [refer to Clause dealing with substitution of Contract Waste] |
BPn | The relevant Base Price per Tonne for Base Price Band 'n', as set out in Appendix 2 |