25.1 This Agreement shall continue in full force and effect from the Commencement Date until the earliest of the following dates:
25.1.1 the Authorities agree in writing to its termination;
25.1.2 there is only one remaining Authority who has not withdrawn from the Agreement in accordance with Clause 22 (Withdrawal during the Procurement Exercise); or
25.1.3 date of execution of the Project Agreement.
25.2 Without prejudice to any other rights or remedies of the Authorities, this Agreement may be terminated in relation to any Authority ("Defaulter") by the other Authorities ("Non-Defaulting Parties") acting unanimously in giving written notice to the Defaulter effective on receipt where the Defaulter is in breach of any of the provisions of this Agreement and, in the case of a breach capable of remedy, fails to remedy the same within five (5) Business Days of being notified of each breach in writing by the Non-Defaulting Parties and being required to remedy the same, or takes an Independent Decision in respect of any matter which has been delegated to the Joint Waste Disposal Committee in accordance with Schedule 11 to this Agreement and which is not a decision specifically reserved to the Defaulting Authority under this Agreement.