[Drafting Note: Authorities should note that these procurement milestones and associated categorisation are indicative only.]
MILESTONE | PROJECT | JOINT | MATTER |
1. Procurement of external advisers to the Project | Yes |
|
|
2. Approval and confirmation of external advisers to the Project |
| Yes |
|
3. Review of the Outline Business Case to be submitted to WIDP |
| Yes |
|
4. Agreement as to recommendation for the Authorities to procure an Option and/or Site. |
| Yes |
|
5. Decision to acquire an option on or any or all of the Sites |
|
| Yes |
6. Drafting and issuing Prior Indicative Notice | Yes |
|
|
41 Preparation of the Descriptive Document and Pre Qualification Questionnaire ("PQQ") | Yes |
|
|
42 Agreeing final version of the Descriptive Document and PQQ |
| Yes |
|
43 Drafting OJEU Notice | Yes |
|
|
44 Agreeing OJEU Notice |
| Yes |
|
45 Issuing OJEU Notice | Yes |
|
|
46 Preparation of Evaluation Criteria for all stages of the procurement process. | Yes |
|
|
47 Agreeing Evaluation Criteria for all stages of the procurement process. |
| Yes |
|
48 Organising open days prior to return of PQQ's and Expressions of Interest | Yes |
|
|
49 Evaluation and Long-listing of Bidders | Yes |
|
|
50 Agreement of long list |
| Yes |
|
51 Inform successful and unsuccessful applicants | Yes |
|
|
52 Drafting ISOS | Yes |
|
|
53 Reviewing ISOS |
| Yes |
|
54 Agreeing ISOS |
|
| Yes |
55 Issue ISOS | Yes |
|
|
56 Arrange the interviews/bidder presentations | Yes |
|
|
57 Evaluation and short listing of ISOS bidders | Yes |
|
|
58 Provisional agreement to ISOS shortlist |
| Yes |
|
59 Final agreement to ISOS shortlist |
|
| Yes |
60 Drafting ISDS | Yes |
|
|
61 Reviewing ISDS |
| Yes |
|
62 Agreeing ISDS |
|
| Yes |
63 Issue of ISDS | Yes |
|
|
64 Evaluation of initial responses to ISDS | Yes |
|
|
65 Organising clarification fmeetings | Yes |
|
|
66 Provisional selection of Bidders to go to Final Stage | Yes |
|
|
67 Review of evaluation and selection of Bidders to go to Final Stage |
| Yes |
|
68 Final approval of evaluation and selection bidders to go to Final Stage |
|
| Yes |
69 Evaluation of final Bids and selection of Preferred Bidder | Yes |
|
|
70 Review of final Bids and selection of Preferred Bidder |
| Yes |
|
71 Agreement to selection of Preferred Bidder |
|
| Yes |
72 Clarification and Final Close 73 Dispatch of Alcatel letters | Yes |
| Yes |
74 Agreement and execution of Project Agreement and Second Inter Authority Agreement |
|
| Yes |
75 Collation of information and provision of information in respect of Project Agreement award procedures required under Regulation 23 Public Services Contracts Regulations | Yes |
|
|
76 Approval of additional expenditure for the Project in excess of the £ million budget referred to in the Outline Business Case |
|
| Yes |
NB Gateway Reviews to be included in the milestones.