Schedule 8 Functions of the Project Team

The functions of the Project Team shall be as follows:

1.  To prepare the draft Business Plan, Work Programme and Resource Plan for recommendation to the Joint Committee.

2.  To monitor implementation of the Project against the approved Business Plan, Work Programme and Resource Plan.

3.  To make such recommendations to the Joint Committee as may be necessary to progress the implementation of the Project.

4.  To give effect to any decisions and instructions of the Joint Committee.

5.  To take such administrative decisions as may be necessary to progress the implementation of the Project.

6.  To ensure that the Project is properly managed.

7.  To give directions to officers in the implementation of the Project.