Supply and management contracts

A management contract is a contractual arrangement for the management of a part or whole of a public enterprise (for example, a specialized port terminal for container handling at a port or a utility) by the private sector. Management contracts allow private sector skills to be brought into service design and delivery, operational control, labour management and equipment procurement. However, the public sector retains the ownership of facility and equipment. The private sector is assigned specified responsibilities concerning a service and is generally not asked to assume commercial risk.

The private contractor is paid a fee to manage and operate services. Normally, the payment of such fees is performance-based. Usually, the contract period is short, typically three to five years4. But the period may be longer for large and complex operational facilities such as a port or an airport.

The main pros and cons of this model include the following:

Pros:

•  Can be implemented in a short time.

•  Least complex of all PPP models.

•  In some countries, politically and socially more acceptable for certain projects (such as water projects and strategic projects like ports and airports).

Cons:

•  Efficiency gains may be limited and little incentive for the private sector to invest.

•  Almost all risks are borne by the public sector.

•  Applicable mainly to existing infrastructure assets.