9.2 After the occurrence of the Actual Completion Date [a Phase Actual Completion Date] the Authority shall grant to Sub-hubco and Sub-hubco Parties, or procure that Sub-hubco and Sub-hubco Parties are granted, access to the Facilities subject only to the Reserved Rights, the Title Conditions and the provisions of this Agreement and solely for the purposes of:
9.2.1 carrying out the Project Operations (other than those Project Operations for which Sub-hubco is granted rights pursuant to Clause 9.1 (Access During Construction));
9.2.2 remedying Defects and carrying out Snagging Matters [relating to that Phase]; and
9.2.3 exercising the Ancillary Rights.
Such rights shall terminate on the Expiry Date or (if earlier) the Termination Date.