11.1 Sub-hubco shall be responsible for:
11.1.1 obtaining all Consents which may be required for the performance of the Project Operations; and
11.1.2 implementing each Consent within the period of its validity in accordance with its terms.
11.2 In the event that:
11.2.1 a Consent that has been granted is subsequently amended, repealed, revoked or otherwise ceases to be in full force and effect in accordance with its terms as a consequence of any action by a Relevant Authority;
11.2.2 affected persons are entitled to claim compensation for the adverse effects of such action under a statutory scheme of compensation; and
11.2.3 Sub-hubco is not entitled in its own name to claim under that scheme but the Authority is so entitled
the Authority must use all reasonable endeavours, at the request and at the cost of Sub-hubco, to claim or to include within its claim such sums as Sub-hubco acting reasonably requests and shall pay to Sub-hubco the part of any compensation that it receives under that scheme that relates to the sums claimed at the request of Sub-hubco.