4 PROCEDURE REVIEW

The Independent Tester shall:

4.1 Monitor the operation of the quality assurance procedures of the Contractor at regular intervals (maximum [three (3)] months) during the execution of the Works.

4.2 The Independent Tester shall familiarise itself with the proposed procedures and programmes for the testing and commissioning of the [Mechanical and Electrical engineering services] prior to the Authority's occupation.

4.3 Monitor the procedures for the identification, approval and recording of agreed Changes to the Works in accordance with the Design Build Finance and Maintain Agreement.

4.4 Review any samples or mock ups as required by Schedule [•] and check that they have been approved in accordance with the Design Build Finance and Maintain Agreement.