2.2  Indemnity

In respect of:

2.2.1  loss of anticipated Revenue during at least the Minimum Indemnity Period arising from a delay in completion of the Project as a result of loss or damage covered under the Contractors' All Risks' Insurance effected in accordance with Item 1 (Contractors' 'All Risks' Insurance (CAR)) of Schedule Part 15 (Insurance Requirements), including physical loss or damage which would be indemnifiable but for the application of any deductible;

2.2.2  the economic additional expenditure necessarily and reasonably incurred for the purpose of avoiding or reducing the loss of Revenue of Sub-hubco which without such expenditure would have taken place, during the Minimum Indemnity Period.