9  Information and notifications by the Authority to Sub-hubco and cooperation of the Authority

9.1  The Authority must notify Sub-hubco as soon as it becomes aware of any matter which may have a reasonably foreseeable material adverse effect on the viability of any High Value Change including any:

9.1.1  planning issues likely to cause a material delay in the anticipated programme for the High Value Change or material cost increases; and

9.1.2  changes to funding which the Authority receives or to the way in which funding may be applied,  either or both of which may affect whether a High Value Change is Affordable.

9.2  The Authority shall provide reasonable assistance to Sub-hubco in relation to the procurement by Sub-hubco of all relevant Necessary Consents.