10  Change Management Fee

The Change Management Fee is to reimburse Sub-hubco for the time spent by its employees in project managing the development, procurement and implementation of the High Value Change and shall:

10.1  be based on actual time spent (validated by time sheets);

10.2  be calculated at the daily rates as set out in Appendix 2 Part 3 to this Schedule Part 16 (Change Protocol), but capped at the sum set out in the High Value Change Proposal;

10.3  not include the time of any person who is not employed by Sub-hubco;

10.4  not include any mark-up or profit or additional overheads;

10.5  be paid in three stages as follows:

10.5.1  on Stage 1 Approval;

10.5.2  on Stage 2 Approval; and

10.5.3  when any works involved in the High Value Change have been completed,

and at each stage Sub-hubco shall charge the Authority (subject to the applicable cap) only for the time incurred by its staff up to completion of that stage.