Grounds for Warning Notices

24.3  If at any time during the Operational Term (other than by reason of a Force Majeure Event, a Relief Event or an Emergency):

24.3.1  the total Deductions for any Contract Month amount to more than [    ] per cent of the Annual Service Payment for the current Contract Year; or

24.3.2  the total Deductions in each of any three Contract Months in any six consecutive Contract Months amount to more than [    ] per cent of the Annual Service Payment for the current Contract Year;

the Authority's Representative may serve a Warning Notice on Project Co, provided always that, to give Project Co time to take appropriate rectification measures, the Authority's Representative shall not be entitled:

(a)  to serve more than one Warning Notice in any month;

(b)  to serve a Warning Notice in any two consecutive months to the extent that the same event has contributed to the Authority's right to serve the Warning Notice, but provided that Project Co demonstrates to the Authority that it has taken all reasonable steps to remedy the cause of that event.